Buying off-plan in Phuket: where buyer protection ends
Since late September I have covered several sales launches on my channel, and two of them have payment schedules. What they share, along with every other schedule I have seen in Phuket: no law makes any of them hold your money in escrow. You pay the developer directly. You can still buy off-plan. Just know exactly where your protection ends before you sign.

| 2-3 years | A normal construction period for a condo project in Phuket. A build running over 4 years is a red flag for financing problems; some projects have been under construction for 6-8 years. |
|---|---|
| 50% | How much of the price you pay before handover in two schedules from my channel: the Sansiri launch in central Phuket (30% at contract, 20% after a year) and the Laguna scheme I covered in August (20% plus three payments of 10%). In the Nai Yang launch it is 75%. |
| 10-12% vs 5-6% | What developers often promise as an annual return, and what often remains after an honest recount of costs. |
| $760,000 (฿24.7M) | A Laguna case from my channel: 121 m² bought for $760,000 (฿24.7M) before construction began; today the cheapest units of that size start from $923,000 (฿30M), on lower floors and without views. |
| $50,000 | The single-transfer amount from which a Thai bank issues the formal Foreign Exchange Transaction form. Below it, you get a credit advice. You need the proof of foreign funds to register freehold. |
Late November. High season in Phuket is under way, and many buyers flying in for December viewings will be shown buildings that do not exist yet. Buying off-plan is paying the developer, on the developer’s schedule, for one of those units. Since late September I have covered several such launches on my channel: Nai Yang in the north, Sansiri in central Phuket, two AssetWise projects on Kata and Karon, and on 22 October I was at the sales launch of a new project in Bang Tao.
So here is the question I want settled before that trip: who protects your money while the building is a fence and a crane? The short answer, as of 21 November 2026: mostly the developer. The bank and the state are not in that picture, and usually neither is an escrow account.
Updated 21 November 2026: the section on construction timelines moved up, now opens with a direct answer and a table of real build schedules from my channel, including the first pile at Saint Tropez in Nai Thon on 13 November, and a note on what a progress report should show. Earlier update, 3 November: high season opening, when the unit legally becomes yours, paying so the FET certificate can be issued, pricing at the Kata and Karon launches. The payment schedules are unchanged.
In Thailand there are still no proper mechanisms to protect the buyer during construction. You give money to the developer directly, and if construction stops, you sort it out yourself. (from my post of 12 August 2026)
That sounds harsh. Off-plan can still work, if you choose the developer the way you would choose a business partner.
Is buying off-plan in Phuket safe? Protection stage by stage
Off-plan goes through four stages, and at each one something different protects you. Here is where each protection ends.
| Stage | What protects you | Where protection ends |
|---|---|---|
| Reservation | Since 31 January 2025, the reservation agreement must follow a standard form. You can terminate if the developer has not obtained the building construction permit by the agreed date, or if a required EIA is not approved | Outside those grounds, the wording of your agreement decides. The booking money is already with the developer |
| Sale contract | The contract must follow the standard form of the Ministry of Interior. The brochure, images and ads are part of the contract, and where they contradict it, the contract is read in your favour | The contract does not hold your money anywhere |
| Instalments during the build | The developer’s record, payments tied to construction stages, the terms written into the contract | Money goes straight to the developer. Escrow is voluntary. If the build stops, you deal with it yourself |
| Completion and transfer at the Land Office | Registration of your title; proof that the money came from abroad; free foreign quota on the day of registration | The quota is checked on that day, not on the day you signed |
The middle two rows are where people lose sleep. The paperwork at the start has improved. The registration at the end is solid. In between, for two or three years, you are lending money to a company.
Neither a signed contract nor full payment makes you the owner yet. Ownership is registered at the Land Office, and only after that is the apartment legally yours. (from my post of 31 October 2026, translated from Russian)
The reservation rule is worth a second look. It appeared because of complaints about confiscated reservation payments. So before any booking, ask for the agreement in the standard form, and read the termination clause yourself.
How reliable are Phuket off-plan construction timelines?
As reliable as the developer’s record, not the brochure. A normal condo build in Phuket takes 2-3 years from the start of works; past 4 years it is a red flag. In March I wrote about a project that started construction and sales in 2017-2018 and in 2026 was still selling and still not completed (my post of 23 March 2026).
Here is how that looks on real projects from my channel, as of 21 November 2026.
| Project | Where it stands | Scheduled completion | What it tells you |
|---|---|---|---|
| Saint Tropez, Nai Thon | First pile driven on 13 November 2026 | End of 2028 | About two years from the first pile, inside the norm if the date holds |
| Sansiri, central Phuket | Sales launch, late September 2026 | Q2 2028 | Counted from launch; first pile date not given |
| AssetWise (The Title), earlier Kata project | Under construction, handover in a year | In about a year, as of 2 November 2026 | Your money waits one year instead of three |
| A project I do not name (post of 23 March 2026) | Building and selling since 2017-2018 | Not completed as of March 2026 | 8 years: a financing problem, and it kept selling |
The Saint Tropez case shows where to start the clock.
This is Nai Thon, the Saint Tropez complex. I bought a studio here myself at the closed sales: 30.62 m² on the 3rd floor for 3,060,000 baht. The studios are now practically gone. A couple are left on the 4th floor, which had been closed to sales, and they already cost 3.8 million baht. (from my post of 13 November 2026, translated from Russian)
That is about $94,000 against $117,000, though on different floors. For timelines, the useful detail is elsewhere. At the closed sales in July, the official start of sales and construction was planned for October, with completion at the end of 2028 (post of 18 July 2026). The pile went in on 13 November. So the countdown starts at the first pile, not at your booking, and a one-month slip at the start does not worry me. A completion date that slides year after year is not.
How to check a developer’s timelines before you pay:
- Ask for the list of completed projects with addresses, and for each one the year it was handed over and whether the date moved. Renders of future projects prove nothing.
- Ask when the first pile went in, or when it is planned. Compare the stage on site today with what the presentation showed.
- Read what the contract says happens if completion is late, and on what terms you can assign the contract if you want to exit before handover.
- If the developer has a nearly finished project, compare it with the new launch. A shorter wait means less time your money sits without an apartment behind it.
While the building goes up, you cannot walk into your condo unit every month. You can follow progress through photos and videos and visit the site when you are on the island. A good progress report gives a stage and pictures that match it. In May I showed one from the project where my mother-in-law bought: about 25% done, the foundation essentially finished, piles in, the first floor going up (post of 6 May 2026). A villa is different: there you can hire separate technical supervision.
At completion comes the handover inspection. Defects turn up almost every time, so they are listed, the developer fixes them, and only then do you sign the acceptance act. If you are not on the island, a representative or an independent inspector can do it, with a photo list of defects.
Does Thailand have escrow for off-plan condos?
On paper, yes: Thailand has an Escrow Act, B.E. 2551 (2008). In practice, for property it is voluntary. The Condominium Act does not oblige developers to use it, and the default on the market is direct payment to the developer.
The contrast is easiest to see next to Dubai, where off-plan is regulated differently.
| Thailand | Dubai | |
|---|---|---|
| Escrow law | Exists, Escrow Act B.E. 2551 (2008) | Law No. 8 of 2007 |
| Is escrow mandatory for off-plan? | No | Yes |
| Who controls the money | The developer, once paid | Escrow account monitored by the Dubai Land Department |
| How the developer gets funds | Directly, on the payment schedule | In stages |
| What protects you during the build | The developer’s record and the contract | The escrow mechanism, plus the developer |
That does not make Dubai the better buy. But in Phuket the job escrow does elsewhere falls on you: checking the company before you pay. You can ask a developer for escrow. Some may agree. Just do not expect it as standard.
How much do you pay before handover?
This is the number that tells you how much is at risk if the build stops. Here are three real schedules from my channel: two launches I covered between 25 September and 6 October 2026, and the Laguna scheme from my post of 11 August. They are cases, not offers.
| Case | At signing | During the build | At or after handover | Paid before keys |
|---|---|---|---|---|
| Nai Yang, one-bedroom 32 m² | Booking $3,080 (฿100,000), then 25% at contract | 25% and 25% | 25% at handover | 75% |
| Sansiri, central Phuket, completion Q2 2028 | 30% at contract | 20% after a year | 50% at handover | 50% |
| Laguna (Banyan Group) | 20% first payment | Three payments of 10% as construction progresses | 50% after handover, over up to 5 years at 7% a year | 50% |
Usually in Phuket the instalments last until handover, and by handover you have paid 100%. Laguna is the exception here: half is paid once the building already stands.
Now in money. Take the 29 m² Sansiri unit at the launch price of $87,000 (฿2,840,000), which is the $92,000 (฿2,990,000) list price minus a $4,620 (฿150,000) discount. At contract you pay $26,220 (฿852,000). After a year, another $17,480 (฿568,000). At handover, $44,000 (฿1,420,000). So $44,000 (฿1,420,000) sits with the developer before you have anything to live in. Dollar figures at an indicative 32.5 ฿/$, October 2026.
The Nai Yang schedule is interest-free over the build, and the discount depends on how you pay: $124,000 (฿4,040,000) on the list, $118,000 (฿3,840,000) with instalments, $112,000 (฿3,640,000) for 100% payment. Paying everything up front buys you a lower price and puts all of it at risk on day one. Weigh that trade before you choose to pay in full.
What I want to see in any schedule: payments tied to construction stages, not to calendar dates alone; any interest clearly stated; the rate fixed in the contract; early repayment without penalties. If the terms are only verbal and the contract wording is vague, I do not go in.
What happens if the developer delays or never finishes?
There is no state body that steps in and finishes the building. No one can guarantee 100% that a project will be completed, and I do not pretend otherwise. Even a reliable project can be delayed: contractors, supplies, documents. A delay alone does not mean anyone planned to cheat you.
What matters is the pattern. A normal construction period in Phuket is 2-3 years. A build running over 4 years is a red flag, usually for financing problems; there are projects here that have been under construction for 6-8 years and are still selling. These are the red flags I look for:
- the build has been going on for more than 4 years;
- investors in the project keep changing;
- the developer pays agents commission in any currency, to any country, without an official agreement;
- the developer has no completed projects.
There is one more thing few buyers know. By Thai law, the company founders will include Thais. So the legal documents tell you only part of the story. Look at the people who really stand behind the project.
How I check an off-plan developer in Phuket
The full company check, from the Thai company register to the EIA and the brand on the facade, is in how to vet a Phuket developer. Here is the short version.
More than a hundred projects are under construction in Phuket right now. Of every ten brought to me, about one reaches my channel. Here is how I filter them.
First, what the company has already built and handed over. Not renders. Buildings that stand, where people live and units are rented out. Banyan Group has worked since 1984 and has built about 3,000 residences in Laguna. You can go and see them.
Second, how long that history is. The shorter it is, the higher the risk. A developer entering Thailand with its first or second project is a high risk for me, and its price must be noticeably below the market to justify it.
There is a company with a second project on the island, and both have stalled. No track record, many questions about the money. Such projects I do not sell, and I tell clients directly: let them finish, then we will talk. (from my post of 31 August 2026)
Third, the questions I ask before any purchase: where the investors are from and who stands behind the project; how many projects are completed; were there delays and how the company got out of them; were delayed projects in the end completed; are the financials transparent. Among the developers I consider reliable are Sansiri, Laguna Property (Banyan Group), Rhom Bho Property (The Title), AssetWise, Wallaya Villas Development, Boat Pattana, Capstone Asset and Origin Vertical.
I do not forbid anyone from buying at the start with a new developer. I name the risk and explain what it is made of. The decision is yours, and so is the responsibility.
Does buying at launch pay off?
Sometimes. Here are two cases from my channel.
Laguna: clients bought 121 m² for $760,000 (฿24.7M) before construction even began. Today the cheapest units of that size start from $923,000 (฿30M), and those are on lower floors without views. On the price list that is a gap of about $163,000 (฿5.3M). It is not profit in hand until someone pays it on resale.
Kata and Karon: AssetWise under its brand The Title has launched two projects, in Kata (135 units, 7 floors) and in Karon (189 units, two buildings of 7 floors). Both are a short walk from the sea; the Karon one I checked myself, see below. Before launch, one-bedrooms were expected from about $123,000 (฿4M). In neighbouring sold-out projects, one-bedrooms from leftover stock go from $169,000 (฿5.5M), and not with the best views. That is the launch logic. Whether this project follows it, nobody knows yet.
On 2 November I came back to these launches with prices in hand.
The launch price is around 160-170 thousand baht per square metre, and you can no longer call that a bargain for a launch. I cannot and will not promise that the units will be worth more by completion. (from my post of 2 November 2026, translated from Russian)
That is about $4,900-5,200 (฿160,000-170,000) per m², and a sea-view unit or penthouse there costs about $6,150 (฿200,000) per m². For this article something else matters more: the same developer has an earlier project in Kata that completes in about a year, with units still available at roughly the same price per m². About three years to handover, or one, is the difference in how long your money sits with the developer without an apartment behind it. At a similar price, the shorter wait lowers the risk in the protection table on its own.
The Sansiri launch discounts ran until 31 October; check current terms on the latest price list. I mention it as a fact of that launch. A discount does not change any row in the protection table above.
Two warnings on returns. Developers often promise 10-12% a year; after an honest recount, 5-6% often remains. For the Sansiri project in central Phuket my own guide is 6-8% a year, and it is a different strategy: annual leases to expats rather than holiday lets. Before you believe any figure, read how gross yield turns into net, and check what the unit earns in the low season.
And the question I ask about every project: who will buy this apartment in five years, and why? In locations where land is still free, new projects will keep appearing and competing with yours.
What to check yourself, not in the presentation
In Karon the developer wrote “450 metres to the sea”. I took a bike and drove it from the site to the beach. 30 seconds by bike, about seven minutes on foot. This time the presentation was honest.
When a presentation says walking distance, I always go and look myself. Too often it means five minutes by car. (from my post of 3 October 2026)
Remember the Condominium Act here: the brochure is part of your contract. So whatever the presentation promises, distance to the beach, facilities, views, keep a copy of it. If it contradicts the contract, the contract is read in your favour.
Expect a compromise too. A client of mine wanted a high floor and chose the third, after seeing the unit in person. Almost every purchase has one. Off-plan, you choose the compromise from a floor plan, so stand on the site and look at what is around it.
How do you prove the money came from abroad?
If you are buying freehold, you will need to show at the Land Office that the purchase money came into Thailand from abroad in foreign currency. Two practical rules:
- The bank issues the formal Foreign Exchange Transaction form (Tor Tor 3) for a single transfer of $50,000 or more. Below that, you get a credit advice. Keep every one.
- The sender’s name must match the buyer’s name. Money sent by a relative or a company can cause problems at registration.
Off-plan payments are often below that threshold. The $26,220 (฿852,000) contract payment on the 29 m² Sansiri unit is below it. So expect a stack of credit advices collected over two or three years. Keep them in one folder from the first payment. For more on the quota itself and what freehold gives you, see freehold vs leasehold in Phuket.
Pay by SWIFT transfer straight to the developer’s account. The FET certificate for the Land Office is issued by the developer’s bank, and only the account holder the money arrived to can get it (my post of 27 October 2026). So decide on freehold or leasehold before the first transfer. I have had clients who first paid as for leasehold, then chose freehold, and the money had to be returned and sent again (post of 29 October).
What to do before a December viewing trip?
The season is already on, and in December many buyers fly in at once. Do the work at home, before the flight:
- Write down the developer’s completed projects and go and see one.
- Get the payment schedule and work out how much you pay before handover, in baht.
- Ask for the reservation agreement in the standard form and read the termination clause.
- Ask whether escrow is available. Note the answer.
- Ask how much foreign quota is left for your specific unit and whether it is written into the contract.
- Plan how the money leaves your bank, in your own name.
- Ask when the building completes, and compare it with a nearly finished project by the same developer.
If you want to see what I currently consider worth looking at, the catalog has it.
Who pays me: the developer pays the agency’s fee out of its sales budget, so selection and deal support are free for the buyer.
The schedule, the developer’s record, the reservation form and the quota are only part of what needs answering before a deal. I have put the full list into a checklist, 30 questions before you sign. Take it to the viewings and ask the developer every question in writing.
FAQ
Is it safe to buy off-plan in Phuket?
It is as safe as the developer. Money usually goes directly to the company, and escrow is not required by law, so if construction stops you deal with it yourself through lawyers. That is why I start with what the developer has already built and handed over. A normal build here is 2-3 years; over 4 years is a red flag. A developer with no completed projects, investors who keep changing, or commissions paid to agents without an official agreement are reasons I do not go in.
Does Thailand have escrow for off-plan condos?
Thailand has an Escrow Act, B.E. 2551 (2008), but for property it is voluntary. The Condominium Act does not oblige developers to use it, and the default is direct payment to the developer. You can ask for escrow, and a developer can agree, but it is not the market norm. Compare Dubai, where Law No. 8 of 2007 requires off-plan developers to use escrow accounts monitored by the Dubai Land Department.
What happens if the developer delays or never finishes?
There is no state mechanism that steps in and completes the building or returns your instalments. You rely on the contract and on the developer. Before buying, ask whether the company has had delays before, how it got out of them, and whether delayed projects were in the end completed. A delay alone does not mean bad faith; a build that drags past 4 years usually means a financing problem.
How much do you pay before construction starts?
It depends on the schedule. In the two launches I covered in late September, Nai Yang asked for a booking of $3,080 (฿100,000) and 25% at contract, and Sansiri in central Phuket asks for 30% at contract. In the Laguna scheme I covered in August, the first payment is 20%. The rest is spread across the build, and in Laguna 50% is paid after handover, over up to 5 years at 7% a year.
Can I get my reservation deposit back?
Since 31 January 2025, condo reservations in Thailand are a contract-controlled business and must follow a standard form. It gives the buyer the right to terminate if the developer has not obtained the building construction permit by the agreed date, or if a required EIA is not approved. Outside those grounds, it depends on the wording of your reservation agreement, so read it before you pay and ask in writing how and when the money is returned.
When is the foreign quota checked?
At transfer, when the unit is registered at the Land Office. What matters is whether there is free foreign quota for your unit on that day. In an off-plan purchase that day can be two or three years after you signed, so ask for the quota for your specific unit to be confirmed in the contract.
How reliable are off-plan construction timelines in Phuket?
As reliable as the developer. A condominium here normally takes 2-3 years to build; more than 4 years is a warning sign, and some projects have been under construction for 6-8 years. A fresh example: at Saint Tropez in Nai Thon the first pile went in on 13 November 2026 with completion scheduled for the end of 2028, about two years, while the start of works had been announced for October. Count from the first pile, not from the booking. Before paying, ask for the developer's completed projects with handover years and any delays, and read what the contract says about late completion.
Sources
- Figures and positions come from Viktoria Shimanovich's own channel posts (in Russian), t.me/vikishiman; each post is at t.me/vikishiman/
: 12 August is 2115, 31 August is 2138, 23 March is 1616, 21 July is 2063, 11 August is 2114, 25 September is 2158, 28 September, 29 September and 6 October are 2167, 2168 and 2192, 5 October is 2185, 30 September is 2172. No proper buyer protection during construction, money paid to the developer directly, Banyan Group since 1984 and the Laguna 121 m² case: post of 12 August 2026. Protection resting on the developer's reliability, the filters, 10-12% promised vs 5-6% after recount, transparent instalments, who buys it in five years, and 'such projects I do not sell': 31 August 2026. Normal build of 2-3 years and the red flags: 23 March 2026. No one can guarantee completion, Thai founders, the developers I consider reliable and the questions to ask: 21 July 2026. The Laguna payment scheme: 11 August 2026. Nai Yang launch: 25 September 2026. Sansiri launch in central Phuket: 28 and 29 September and 6 October 2026. The 450 metres check in Karon: 3 October 2026, t.me/vikishiman/2178. AssetWise (The Title) in Kata and Karon and the 17 October presentation: 5 October 2026. The third-floor compromise: 30 September 2026. - Escrow Act B.E. 2551 (2008), voluntary for property; the Condominium Act does not oblige developers to use escrow: Tilleke & Gibbins, using Thailand's Escrow Act in property development; Thai Law Online, escrow accounts in Thailand, 2026 guide.
- OCPB notification making condo unit reservation a contract-controlled business, published in the Government Gazette on 3 October 2024, in force 120 days later, on 31 January 2025, with a mandatory reservation form, introduced to address consumer complaints about confiscated reservation payments: Baker McKenzie; Tilleke & Gibbins, form of reservation contract.
- The foreign quota is a share of the building's floor area under section 19 of the Condominium Act, and a unit can be registered to a foreigner only if quota is free on the day of registration: Tilleke & Gibbins, inheritance of condominium units by foreigners; terms.law, condominium foreign quota.
- Condominium Act B.E. 2522 (1979), sections 6/1 (advertising is part of the sale contract and is read in the buyer's favour) and 6/2 (standard form of sale contract): English translation of the Act, Thailand Law Online; Thai Law Online, off-plan condo in Thailand.
- Foreign Exchange Transaction form (Tor Tor 3), formal FET form for single transfers of USD 50,000 or more, credit advice below that, sender name to match buyer: Emerhub; Lazudi.
- Dubai, Law No. 8 of 2007 on escrow accounts for off-plan developments: Dubai Legislation Portal%20of%202007.html).
- Dollar conversions are at an indicative 32.5 baht per dollar; the 2026 year-to-date average was 32.31: USD/THB history 2026.
- Channel posts behind the 3 November update: 27 October 2026 (SWIFT to the developer's account, FET certificate, completed projects with handover years and delays, assignment, handover by an inspector), 29 October 2026 (paid as leasehold, then switched to freehold), 31 October 2026 (owner only after Land Office registration, progress by photo and video, technical supervision for villas, defects at handover), 26 October 2026 (Bang Tao sales launch on 22 October), 2 November 2026 (160-170 thousand baht per m² at the Kata and Karon launches, about 200 thousand for sea views, first Kata project completing in a year). The developer pays the agency's fee and the service is free for the buyer: 17 December 2024.
- Channel posts behind the 21 November update: 13 November 2026 (first pile at Saint Tropez, Nai Thon; studio of 30.62 m² on the 3rd floor bought at closed sales for 3,060,000 baht, remaining 4th-floor studios at 3.8 million baht), 18 July 2026, 3 August 2026 and 6 August 2026 (closed sales of the same Nai Thon project, 30.6 m² studio: official start of sales and construction planned for October, completion at the end of 2028, 4th floor not yet open), 6 May 2026 (about 25% complete, foundation done, piles in, first floor going up), 23 March 2026 (a project building and selling since 2017-2018, not completed in 2026). Completion of Saint Tropez as 2028-Q4 also in the catalog card.
- The projects named here are cases from my channel, not offers. Prices, discounts and schedules are as of the dates of the posts and change.
- This is not legal advice. Have the reservation agreement, the sale contract and the payment route checked before payment by a lawyer who works only with property in Thailand.













